199. As per the table below, the EAC is:
Task 1: $2000(estimate to be completed by 30th sept)
Task 2: $1500(estimate to be completed by 30th sept)
Task 3: $1000(estimate to be completed 50% by 30th sept)
task 4: $900 (estimate to be completed 10% by 30th sept)
Task 5: $1000 (estimate to be completed by 30th sept)
a)6090
b)6400
3)6128
d)1628
correct answer:6128
comment:EAC=BAC/CPI
200.A team member does some changes in the project without anyone's consent. As per the opinion, later obtained from an expert, it was observed that the changes were required. This is an example of?
a)Self motivated team
b)Value added change
c)Ineffective change control
d)cost control
Correct answer:Ineffective change control
Task 1: $2000(estimate to be completed by 30th sept)
Task 2: $1500(estimate to be completed by 30th sept)
Task 3: $1000(estimate to be completed 50% by 30th sept)
task 4: $900 (estimate to be completed 10% by 30th sept)
Task 5: $1000 (estimate to be completed by 30th sept)
a)6090
b)6400
3)6128
d)1628
correct answer:6128
comment:EAC=BAC/CPI
200.A team member does some changes in the project without anyone's consent. As per the opinion, later obtained from an expert, it was observed that the changes were required. This is an example of?
a)Self motivated team
b)Value added change
c)Ineffective change control
d)cost control
Correct answer:Ineffective change control
1 comment:
Thanks for sharing this post.
Interview Questions
Post a Comment